Hi there,
i'm using BrightStor ArcServe Backup for Windows 9.01 and here is the description about my issue:
By using ArcServe i backup a server called TEST and have added a
PRE-execution job called TESTX for this backup.
Now it takes 1 hour to run and finish the program TESTX which ok.
What i want is:
1) backup process starts 17:00
2) PRE-execution job TESTX is executed 17:01
3) PRE-execution job TESTX is ready 18:00
4) backup process continues after the program is run and finished 18:01
This is what i get:
1) backup process starts 17:00
2) PRE-execution job TESTX is executed 17:01
3) PRE-execution job TESTX is left running on the machine
4) backup process continues instantly after the program is executed 17:01
But i want the program to run and finish before the backup process continues, is this possible at all?!