    Unanswered: challenge - display entries week by week

    Hi

    I'm producing a project time report system. team members
    enters time spent on a project in a database.
    my question is how do i produce a report that writes out
    on a "week by week" basis for a whole year or quarter, how
    much time is spent on each project ? the report therefore
    needs to show the date at the beginning of the week and the time spent on a project.

    so for example once i execute this report it'll show something like below.



    Week 01-10 08-10 15-10 22-10 |total ---> goes onto end of quarter
    --------------------------------------|-----
    Total 5.0 5.0 5.0 5.0 | 20
    --------------------------------------|-----
    Project|
    -------|
    CP9 |0.0 0.0 0.0 0.0 | 0
    -CP9.1 |0.3 0.0 0.0 0.0 | 0.3
    -CP9.2 |0.4 0.0 0.0 0.0 | 0.4
    -CP9.3 |0.5 0.0 0.0 0.0 | 0.5
    |
    CP10 |0.0 0.0 0.0 3.1 | 3.1
    -CP10.1|0.0 0.0 0.0 0.0 | 0
    -CP10.2|0.0 0.0 0.0 0.3 | 0
    -CP10.9|0.0 0.0 0.0 0.0 | 0
    |
    CP11 |1.4 2.2 0.8 0.5 | 7.9
    -CP11.1|0.6 2.1 0.4 0.1 | 3.2
    -CP11.2|0.8 0.1 0.4 0.4 | 1.7


    I understand how to use the sorting and grouping function
    of reports but can't figure out how to write out a date
    for every week plus i've got a feeling that the formatting will be a
    nightmare. I'm using access 97 as well.

    anyone up for a challenge ?

    Joe

  2. #2
    Join Date
    Feb 2002
    Posts
    403
    I vaguely remember reading somewhere about Week(num) function have a look in help under week. This function returns the week number of the year and is a more normal reference for project teams (in contstruction anyway) for gannt charts and the like.